Programs move through a defined lifecycle. Understanding each stage helps you plan your training rollouts and manage programs effectively.

Program Statuses

StatusWhat is happeningWhat you can do
In DesignBuilding the program. Adding components and configuring settings.Add/edit/remove components, enroll participants, set dates
Launch ReadyThe program has at least one component and enrolled participants. Ready to go live.Everything from In Design, plus launch the program
LiveParticipants have been notified and are working through components.Monitor progress, adjust components, grant extensions, close components early, end the program
CompleteThe program has ended. All statuses are finalized.View final results
ArchivedThe program was removed before it launched.View archived program (read-only)

Automatic Transitions

The transition between In Design and Launch Ready is automatic. When your program has at least one component and enrolled participants, the status moves to Launch Ready. If you remove all components or participants, it moves back to In Design. All other transitions are manual - you decide when to launch, end, or archive.

Preparing to Launch

When your program reaches Launch Ready status, the program dashboard shows a launch checklist:
Program dashboard showing completed program with components and program leads
1

Decide participants

Confirm that the right people are enrolled. The checklist shows whether participants have been added.Manage participants ->
2

Schedule launch emails

Optionally configure pre-launch communications. The recommendation is to send at least two emails from you or an influential leader before the automated enrollment email goes out. Mark this step as complete when ready.
3

Automated enrollment email

When the program launches, an automated email goes to all enrolled participants:
Subject: “Please read: You’re enrolled in [Program Name]” From: [email protected]
The email is sent on the launch date you configured.

Launching a Program

You have two options for launching:

Launch Now

Click Launch Now on the launch panel. A confirmation dialog appears:
“All of your participants will be notified. This is not reversible.”
Click Launch Now to confirm. The program immediately becomes Live.

Schedule for Later

If your target launch date is in the future, the program launches automatically when that date arrives. You can also click Edit Schedule to change the launch date and time.

What Happens at Launch

When a program launches, several things happen automatically:
  1. Status changes to Live
  2. Enrollment emails are sent to all participants
  3. Components set to auto-launch have their launch dates synced to the program’s launch date
  4. Roleplay scenario permissions are synced so participants can access assigned scenarios
  5. Program leads receive a “program is live” notification email
Launching cannot be undone. Once a program is live, you cannot return it to In Design or Launch Ready. Make sure components, participants, and dates are set before launching.

Managing a Live Program

While a program is live, you can:
  • Add new components: New activities can be added at any time
  • Edit existing components: Update dates, content, participants, and settings
  • Close components early: End a component before its scheduled close date. This finalizes participant statuses for that component.
  • Grant deadline extensions: Give participants more time on specific components
  • Send nudges: Remind participants to complete pending work
  • Add participants: New participants can be enrolled into a live program. They gain access to all “all participants” components.
  • Remove participants: Remove someone who should no longer be in the program

Ending a Program

When your program’s training period is over, end it to finalize results.
1

Open the actions menu

From the program dashboard or the programs list, click the actions menu and select End Program.
2

Confirm

A confirmation dialog explains what will happen:
  • All ongoing components are closed (participant statuses are finalized)
  • All upcoming and in-design components are removed
  • The program status changes to Complete
3

Review results

After the program ends:
  • Program leads receive a completion email with pass/fail statistics
  • Participants receive a status notification email
  • If a certification is linked, certificates are automatically issued to participants who completed all required components
When a program ends, each participant’s final status is calculated based on their completion of required components. Participants who completed all required components are marked Complete. Those who did not are marked Did Not Pass. Optional components do not count toward this calculation.

Archiving a Program

Archiving is for programs that were never launched. It removes the program from your active list and cancels any scheduled invitations.
1

Open the actions menu

From the programs list, click the actions menu on the program you want to archive and select Archive.
2

Confirm

A confirmation dialog explains what will happen:
  • Scheduled participant invitations are cancelled
  • Reserved credits are restored to your workspace account
  • The program moves to Archived status
You can only archive programs that have not been launched (In Design or Launch Ready status). Once a program is live, you must end it instead.

Lifecycle Summary

In Design  ──→  Launch Ready  ──→  Live  ──→  Complete
    │                │
    └── Archive      └── Archive
  • In Design and Launch Ready can be archived
  • Live can only be ended (Complete)
  • Complete is a final state

Program Notifications

Exec sends automatic email notifications at key points in the program lifecycle. All program emails are skipped for demo programs.

Notification Reference

NotificationWhen it’s sentWho receives it
Enrollment emailWhen participants are added to the programNew participants
Program liveWhen the program launchesProgram leads only
Component launchWhen a component’s start date arrives (checked every 5 minutes)Participants assigned to that component
Component reminderBefore the component due date (configurable per component)Participants who haven’t completed it
NudgeManually triggered by a lead or adminSelected participants (15-minute cooldown per person)
Coaching introWhen a 1:1 coaching component launchesParticipants who need to select a coach
Coaching reminderEvery 3 days while coaching intro is activeParticipants who haven’t booked a session
Program endedWhen the program is endedLeads (with pass/fail stats) and participants (with their status)

Component Launch Emails

When a component’s start date arrives and the program is live, Exec automatically sends a launch email to all participants. The email content varies by component type:
  • Surveys, Action Items, Articles, Videos - “Please take the [component name]” with a link to complete it
  • Announcements - The announcement content is included directly in the email body
  • 1:1 Coaching - “Find My Coach” prompt with a link to select a coach
Component launch emails are only sent once per participant per component. If you change a component’s start date after it was already sent, participants who already received the email won’t get a second one.

Automatic Reminders

Exec can send reminder emails before a component’s due date. These are configured per component when you set it up. Reminders are checked hourly and sent once per participant per component.
For urgent follow-ups, use the manual nudge feature instead of waiting for automatic reminders. Nudges can be sent at any time with a 15-minute cooldown between sends to the same person.

Getting Help

Need help managing your program lifecycle? Contact us at [email protected].